Fusion Splicer  Fiber connecting the process and steps
    1) stripping fiber optic cable and fiber optic cable fixed to the plate rack. Common fiber optic cable has twist-type layer, skeleton and central beam tube fiber optic cable, a different cable stripping to take a different approach, after stripping a good fiber to fiber frame fixed to the plate.
    
2), respectively, through the fiber heat-shrinkable tube. Different beam tube, different colors of fiber separation, through the heat shrink tubing. Welding is completed, you can use heat shrink tubing to protect fiber splices head.
     
3) Open the welding machine power source, select the appropriate welding method. Welding machine power supply with AC and DC, according to the type of power supply to a reasonable switch. We know, CATV fiber using a conventional type of single-mode fiber and dispersion shifted single-mode fiber, Wavelength 1310nm and 1550nm are also two, so we have to use the system and the operating wavelength of the optical fiber to select the appropriate welding method.
   
4) to prepare the fiber end. Fiber production will directly affect the continuation of quality as in the welding, you must first make a qualified face. With a special stripping tool strip coating, cleaning with alcohol and then stained linen or cotton, wipe a few times on the bare fiber, using precision fiber cleaver cutting fiber of 0.25nm (outer coating) fiber, cutting length of 8mm-16mm, for 0.9mm (outer coating) fiber, cut length of only 16mm.
   
5) placed fiber. The fiber on the welding machine V-shaped slot, and careful pressure on the optical fiber fixture plate, according to the optical fiber cut length is set in the position of the platen, and correctly placed in the windscreen.
    
6) connecting fiber. Press the continue button, the fiber moving towards each other and on the move, resulting in a short discharge cleaning the fiber surface, when the gap between the fiber end after the welding machine suitable to stop moving towards each other, set the initial gap, welding machine measurement and display cutting angle. After setting the initial gap, started targeting core or cladding, and welding machines reduce the gap (the last gap setting), high-pressure arc discharge generated by melting the left to the right optical fiber, the last micro-processing calculates the losses and the value displayed on the monitor. If the estimated loss of value to be higher than expected, you can re-discharge, discharge welding machine will calculate the loss.
    
7) out of the optical fiber and reinforced with a heater. Open the windscreen, will pick the same time welding data storage. These include: Weld mode, data, estimate the wear and tear. The fiber removed from the welding machine, and then heat shrink tubing on the bare fiber center, put the heater in the heating, after the fiber removed from the heater. Operation, the temperature is high, do not touch the heat shrink tube and the ceramic heater portion.
    
8) disk fiber and fixed. Will continue to splice a good optical disk drive, fixed optical fiber, shelter plate, connector boxes, terminal box, etc., fiber splicing completed.
   
9) Optical Fiber Fusion Splicer wearing parts for the discharge electrodes, each manufacturer has different advice, but basically 4000 to 5000 times the discharge of the electrode to be replaced like a. Or do something in their own treatment, re-polished, but the length will change, the corresponding welding parameters will make changes because as